2025 TIP Amendment Calendar

Please refer to the schedule below to determine when to submit applications to amend the TIP. Note that some applications are subject to board approval. For more information on determining whether your project is subject to this provision, please consult PSRC’s Amendment Review Process.

There are no STIP amendments in November and December.

FOR THE MONTH OFAPPLICATION DEADLINEADDED TO AMENDMENT #AMENDMENT SUBMITTED TO STATE DOT BY PSRCAPPROVED IN STATE TIP
January12/6/202425-011/17/2025Mid-February
February1/17/202525-022/21/2025Mid-March
March2/14/202525-033/21/2025Mid-April
April3/14/202525-044/18/2025Mid-May
May*4/11/202525-055/16/2025Mid-June
June5/16/202525-066/20/2025Mid-July
July6/13/202525-077/18/2025Mid-August
August *7/11/202525-088/15/2025Mid-September
September8/15/202525-099/19/2025Mid-October
October9/12/202525-1010/17/2025Mid-November

* Note: PSRC boards do not meet every month. The table above identifies the standard months when the boards do not meet; however, this is subject to change. Projects requiring Board approval during months when the Boards do not meet will be processed the following month. Sponsors should consult the list of upcoming PSRC meetings  and take this information into consideration in order to meet project deadlines.

Amendment Schedule

Monthly routine amendments are generally submitted to Washington State Department of Transportation (WSDOT) for inclusion in the State TIP, usually on the third Friday of each month. Final approval by the Federal Highway Administration (FHWA) and Federal Transit Administration (FTA) normally takes an additional three weeks before amendments will be included into the State TIP. Once PSRC receives verification of federal approval, all sponsors with projects in a given amendment will be notified electronically. In addition, this page hosts the list of Recent Amendments and Appendix A of the Regional TIP which are updated to include a list of all projects in the approved amendment.

Image
Graphic of amendment approval process. 2 months to complete